Illustrative image – not actual.Nine power projects, including one in the private sector and eight in the State / Central sector, are currently under examination with the Central Electricity Authority (CEA). This was stated by the Minister of State for Power, Ms Jayawanti Mehta in Parliament, on 21 November 2001.
The Minister stated that the projects would be considered for accord of Techno Economic Clearance (TEC) by the CEA as soon as pending essential inputs and clearances are tied up by the project authorities concerned.
The details of these pending power projects are as follows:
|
Name of project |
Capacity (MW) |
Estd. cost incl. IDC (Rs.cr.) |
Receipt of DPR in CEA |
|
1.Rajgarh CCPP (Madhya Pradesh)-Thermal |
343.48 |
1128.78 |
10.3.97 |
STATE / CENTRAL SECTOR SCHEMES:
|
Name of project |
Capacity (MW) |
Estd. cost incl. IDC (Rs.cr.) |
Receipt of DPR in CEA |
|
2. UHL HEP St.III (H.P.)-(HPSEB) Hydro |
100 |
464.80 |
4.11.99 |
|
3. Koldam HEP (NTPC) (H.P) - Hydro |
800 |
4043.08 |
6/01 |
|
4. Kota TPS U-6 St.IV
(RRVUNL)-(Rajasthan) –Thermal |
195 |
635.00 |
6/01 |
|
5. Feroz Gandhi Unchahar TPS St.III
(NTPC) (U.P) - Thermal |
490 |
2401.15 |
8/01 |
|
6. Valuthur (Perungulam) (T.N.E.B) - Thermal |
95 |
343.75 |
5.7.2000 |
|
7. Bakreshwar TPS U-4&5 (WBPDCL)-Thermal |
420 |
1479.00 |
4/01 |
|
8. Kahalgaon STPP St.II (NTPC) (Bihar)-
Thermal |
1320 |
4669.22 |
3/2000 |
|
9. Monarchak CCPP (NEEPCO)-(Tripura)-
Thermal |
500 |
2359.73 1849.42 (Revised) |
4/2001 |