Illustrative image – not actual.The repair of the bridge involves bearing and expansion joint replacement and it is planned to be executed in two phases, with each phase focusing on one lane of the bridge at a time. Phase-I will see construction work implemented on the lane inbound Apapa while Phase-II will focus on the lane that conveys vehicles outside the axis.
A contraflow of 200 mtr has also been designed for vehicles to realign with a proper direction inward Ajegunle or Wharf Road, Apapa, and motorists descending to Total Gas would drive through without any interferences.