NHSRCL inks pact to execute electrical works on Ahmedabad-Mumbai rail projectIllustrative image – not actual.

National High Speed Rail Corporation (NHSRCL) has signed an agreement for executing electrical works on the Ahmedabad-Mumbai high-speed rail project.

The company awarded the contract will be responsible for works, which include designing, manufacturing, supplying, construction, installation, testing and commissioning of 25 kV electrification systems suitable for speeds up to 320 km/hour. The land required for constructing the BKC station, which is about 4.8 hectares, has been handed over to the contractor by NHSRCL.

The station will be built using the bottom-up method, which means that excavation work will commence from the ground level, and concrete work will start from the foundation. The excavation required for the station is extensive, reaching a depth of 32 mtrs., with an approx. volume of around 18 lakh cubic mtrs. The excavation in the station area has already been commenced. To construct this tunnel in Maharashtra, tunnel boring machines (TBMs) with a cutter head of 13.6 mtrs. diameter will be used.

Three TBMs will be used to make about 16 km of the tunnel portion and the remaining five km will be through a new Austrian tunnelling method (NATM). This tunnel will be about 25 to 57 mtrs. deep from the ground level and the deepest construction point will be 114 mtrs. below the Parsik Hill near Shilphata. Three shafts at Bandra-Kurla Centre, Vikhroli, and Sawli at approx. depths of 36, 56 and 39-mtrs., respectively will facilitate the construction.

The inclined shaft of 42 mtrs. at Ghansoli and the tunnel portal at Shilphata will facilitate the construction of approx. five km of tunnel through the NATM tunnelling method. Currently, there are 681 labourers and supervisors on-site working. This number is expected to increase as the project advances.