Illustrative image – not actual.NHPC is facing delay in completing its Subansiri lower hydroelectric power project at the lower reaches of River Subansiri, Hapoli (Ziro) in Lower Subansiri district of Arunachal Pradesh.
The project, with 2,000 MW capacity, was originally scheduled to be completed by September 2010, but the complete work has come to a standstill since December 2011 due to agitation by various activists citing risks of landslides in the region, downstream impacts, flood control, and ecological damages to aquatic wealth and earthquakes.
To tackle the issues of the agitating group, NHPC intends to make changes in design of dam structure, which will have effects on the construction schedule of the project. Taking note of this, NHPC has revised the completion schedule for the project. Moreover, support from the state government will help the company to commission the project on schedule.
The company is setting up the project in eight phases with an investment of Rs 7,451.99 crore.