Illustrative image – not actual.The National Hydroelectric Power Corporation’s (NHPC) Parbati Stage-II project will become operational in mid-September 2018. The project is located across Parbati river, in Kullu district of Himachal Pradesh.
NHPC has begun the testing for power generation at Parbati Stage-II. The Parbati river is proposed to be diverted with a concrete gravity dam at Pulga village in Parbati valley through 31.52 km long head race tunnel.
The project authority has already started water storage through 31.52 km long head race tunnel to test the leakage of water and other technical aspects.
Former Prime Minister Atal Bihari Vajpayee had laid the foundation stone of the Parbati project in the year 2000. The project was supposed to be commissioned in 2007 and will produce power of 3,160.66 million units every year. The project has been surrounded by problems right from the inception stage.