NHPC's floating solar project in Kerala set for 2027 commissioningIllustrative image – not actual.

The fifty-MW floating solar power project being implemented by the National Hydroelectric Power Corporation (NHPC) at West Kallada is officially scheduled for commissioning in March 2027.

According to Member of Parliament Kodikunnil Suresh, the total investment for the initiative stands at approx. Rs 260 crore, encompassing five years of operation and maintenance. The facility is projected to generate roughly 99 million units of electricity during its inaugural operational year. Although originally conceptualised in 2013, the venture gained renewed momentum after NHPC and the Kerala State Electricity Board (KSEB) signed a power purchase agreement (PPA) in April 2025, followed by a formal foundation stone laying ceremony in March 2026.

Additionally, local panchayat authorities intend to develop an adjacent one-hundred-acre segment of the water area into a vibrant tourism hub featuring water sports and boating activities.

 