NHPC to start trial run of unit 4 of Teesta projectIllustrative image – not actual.

NHPC is likely to commence trial run of unit 4 of its Teesta Low Dam hydel power project stage III at Darjeeling in West Bengal on 1 May, 2013.


NHPC will start trial run and demonstration of peaking capability corresponding to installed unit 4 of the project on 1 May, 2013. Unit-4 of the project has the capacity of 33 MW.


NHPC is constructing Teesta stage III hydel project with an investment of Rs 1,073.29 crore. The project (4x33 MW) is a part of the Teesta Low Dam Hydroelectric Project.


On 1 April, 2013, the company  commenced commercial operation of Unit-2 & Unit-3 of the project.