Illustrative image – not actual.National Hydro-electric Power
Corporation (NHPC) has stated that it would complete the third and fourth stage
of the Teesta Low Dam Project by the year 2004, one year before schedule.
The
Teesta Power Project would generate hydel power by harnessing the Teesta river
that originates in Sikkim and flows through North Bengal. The power generating
capacity envisaged is 332 MW of which 100 MW would be in Sikkim and 232 MW in
West Bengal. The project has been split into four stages in the following
manner:
|
Stages |
State |
Capacity
(MW) |
|
I
& II |
Sikkim |
100 |
|
III
& IV |
West
Bengal |
232
(100 + 132) |
Talks
with the Sikkim government would be held soon while those with the West Bengal government
have progressed significantly. NHPC signed a memorandum of understanding with
the West Bengal State Electricity Board on 10 November 2000.
For
that part of the project in West Bengal, NHPC is planning to prepare the
detailed project report by March 2001 and project work is expected to start in
November 2001.
The total cost of the project is
expected to be Rs.636 crore for Stage III and Rs.939 crore for Stage IV. The
overall cost of generation is likely to be around Rs.1.50 per unit.
|
Stage |
Capacity
(MW) |
Total
Cost (Rs.crore) |
Cost
per MW (Rs.crore) |
|
III |
100 |
636 |
6.36 |
|
IV |
132 |
939 |
7.11 |
|
Total |
232 |
1,575 |
6.79 |