NHPC to complete Teesta Low Dam schemes before scheduleIllustrative image – not actual.

National Hydro-electric Power Corporation (NHPC) has stated that it would complete the third and fourth stage of the Teesta Low Dam Project by the year 2004, one year before schedule.

 

The Teesta Power Project would generate hydel power by harnessing the Teesta river that originates in Sikkim and flows through North Bengal. The power generating capacity envisaged is 332 MW of which 100 MW would be in Sikkim and 232 MW in West Bengal. The project has been split into four stages in the following manner:

 

Stages

State

Capacity (MW)

I & II

Sikkim

100

III & IV

West Bengal

232 (100 + 132)

 

Talks with the Sikkim government would be held soon while those with the West Bengal government have progressed significantly. NHPC signed a memorandum of understanding with the West Bengal State Electricity Board on 10 November 2000.

 

For that part of the project in West Bengal, NHPC is planning to prepare the detailed project report by March 2001 and project work is expected to start in November 2001.

 

The total cost of the project is expected to be Rs.636 crore for Stage III and Rs.939 crore for Stage IV. The overall cost of generation is likely to be around Rs.1.50 per unit.

 

Stage

Capacity (MW)

Total Cost (Rs.crore)

Cost per MW (Rs.crore)

III

100

   636

6.36

IV

132

   939

7.11

Total

232

1,575

6.79

 

 