Illustrative image – not actual.NHPC is likely to commission five delayed projects by March 2018.
The five projects with 3,810 MW capacity which were envisaged earlier, got stuck due environmental or contractual issues.
Of the five projects, the Subansiri Lower project in Arunachal Pradesh, with 2,000 MW capacity, was expected to be commissioned by December 2012, and is now likely to become operational by December 2017. It had been delayed since December 2011, after the local people raised issues related to its safety and downstream impact.
Similarly, the 520 MW, Parbati-III in Himachal Pradesh, which was stalled due to contractual issues, will now be commissioned in March 2014. The project was delayed by over three years from its original schedule of November 2010. Further, Parbati-II with 800 MW capacity will be commissioned in March 2018.
The Teesta Low Dam Project-IV in West Bengal with 160 MW capacity, and Kishanganga in Jammu and Kashmir with 330 MW capacity, will be completed by November 2014 and November 2016, respectively.
Recently, the company commissioned its Uri-II power project with 240 MW capacity.