Illustrative image – not actual.National Hydroelectric Power Corporation has planned to make capital expenditure of Rs.3,312 crore in 2006-07 with an aim to add 900 MW of fresh power capacity. NHPC expects Rs.1,374 crore as gross budgetory support while the remainder would come from internal accruals.
NHPC does not expect major market borrowings during FY07 since it has already tied up with Life Insurance Corporation of India for long term credit of Rs.9,000 crore.
In 2006-07, NHPC has targeted to commission the 390 MW Dulhasti project in Jammu & Kashmir (June 2006) and the 510 MW Teesta-V project in West Bengal (February 2007).
Meanwhile, NHPC is likely to raise $100 million concessional loan as export credit assistance from Coface of France for its 2,000 MW Lower Subansiri power project in Arunachal Pradesh. In March 2005, the electro-mechanical package for this project was awarded to Alstom of France.
It is also likely that the 11,000 MW Upper Siang Project in Arunachal Pradesh would be downscaled to 7,000-8,000 MW in response to apprehensions expressed by China.
Vision 2012: The hydropower major's vision for 2012 is to touch capacity of 7,707 MW from the current 3,755 MW. The Rs.60,000 crore expansion plan will be financed through market borrowings of around Rs.27,000 crore.