Illustrative image – not actual.NHPC has set a consolidated capital expenditure target of Rs 15,000 crore for FY2026-27 as it expands its hydropower, solar, energy storage and renewable-energy portfolio.
NHPC’s solar construction pipeline includes projects at Khavda in Gujarat, Andhra Pradesh, Odisha, and other locations, with a combined estimated investment of Rs 6,901.47 crore. The 200 MW Khavda project is scheduled for commissioning in September 2026, and will be followed by Andhra Pradesh and Odisha projects. Separately, NHPC’s subsidiary is developing a 1,200 MW solar park in Jalaun, Uttar Pradesh. The company is also exploring battery energy storage integration, supporting its broader renewable-energy expansion strategy.
The company currently operates 9,333 MW across 31 power stations, including 8,771 MW of hydropower and 562 MW of solar and wind capacity. Another 9,204 MW is under construction, while 10,263 MW awaits clearances and approvals.