NHPC targets 30,310 MW generating capacity in 15 yearsIllustrative image – not actual.

National Hydro-Electric Power Corporation (NHPC) has plans to invest Rs.1,95,000 crore for adding 30,310 MW of generating capacity in the next 15 years. This was stated by NHPC’s chairman and managing director, Mr Yogendra Prasad.

 

Of this amount, NHPC plans to invest Rs.40,000 crore during the 10th Five Year Plan, Rs.57,000 crore during the 11th Five Year Plan and the balance during the 12th Five Year Plan.

 

NHPC investment plans for the 10th 11th & 12th Plan Periods are:

 

Plan Period

Investment

(Rs.cr)

Target Generation

Capacity (MW)

2002-07

40,000

5,310

2007-12

57,000

11,500

2012-17

98,000

13,500

Total

1,95,000

30,310

 

Of the 5,310 MW power generation capacity that NHPC proposes to add during the 10th Plan, work contracts for 3,500 MW have already been awarded.

 

Presently, NHPC is working on five projects, viz. Dul Hasti (390 MW, J&K); Dhauliganga Stage I (280 MW, Uttaranchal); Chamera (300 MW, HP); Loktak downstream (90 MW, Manipur) and Teesta Stage V (510 MW, Sikkim).