Illustrative image – not actual.National Hydro-Electric Power Corporation (NHPC) has plans to invest Rs.1,95,000 crore for adding 30,310 MW of generating capacity in the next 15 years. This was stated by NHPC’s chairman and managing director, Mr Yogendra Prasad.
Of this amount, NHPC plans to invest Rs.40,000 crore
during the 10th Five Year Plan, Rs.57,000 crore during the 11th
Five Year Plan and the balance during the 12th Five Year Plan.
NHPC investment plans for the 10th 11th
& 12th Plan Periods are:
|
Plan
Period |
Investment (Rs.cr) |
Target
Generation Capacity
(MW) |
|
2002-07 |
40,000 |
5,310 |
|
2007-12 |
57,000 |
11,500 |
|
2012-17 |
98,000 |
13,500 |
|
Total |
1,95,000 |
30,310 |
Of the 5,310 MW power generation capacity that NHPC
proposes to add during the 10th Plan, work contracts for 3,500 MW
have already been awarded.
Presently, NHPC is working on five projects, viz. Dul
Hasti (390 MW, J&K); Dhauliganga Stage I (280 MW, Uttaranchal); Chamera
(300 MW, HP); Loktak downstream (90 MW, Manipur) and Teesta Stage V (510 MW,
Sikkim).