Illustrative image – not actual.National Hydroelectric Power Corporation (NHPC), which plans to implement 16 hydel power projects with a total capacity of 7,268 MW during the Tenth Plan period (2002-07), has sought budgetary support of Rs.22,000 crore for these projects.
NHPC has already submitted its proposal to the Union Ministry of Power for its approval. The latter is considering NHPC’s proposal.
The projects are proposed to be
implemented on a debt-equity ratio of 70:30. The investment is expected to be
around Rs.5 crore per MW.
|
Project |
State |
Capacity (MW) |
|
Subansiri lower |
AP |
2,000 |
|
Indira Sagar |
MP |
1,000 |
|
Purulia |
WB |
900 |
|
Upper Krishna |
Kar |
810 |
|
Omkareshwar |
MP |
520 |
|
Teesta-V |
Sikkim |
510 |
|
Dulhasti |
J&K |
390 |
|
Chamera-II |
UP |
300 |
|
Dhauliganga-I |
HP |
280 |
|
Teesta Low Dam-IV |
WB |
132 |
|
Farakka Barage |
WB |
125 |
|
Sewa-II |
J&K |
120 |
|
Teesta Low Dam-III |
WB |
100 |
|
BAV-II |
Mah |
37 |
|
Deoli |
Mah |
26 |
|
BAV-I |
Mah |
18 |
|
Total |
|
7,268 |
NHPC has also
identified 22 more projects with a total capacity of 11,410 MW, to be
implemented during the Eleventh Plan period (2007-12).
NHPC has also shortlisted 12 projects with a total capacity of 23,071 MW for international and joint venture collaboration. These projects, which would be developed in Arunachal Pradesh, Himachal Pradesh and Jammu & Kashmir, are expected to involve an investment of Rs.1,15,350 crore.
|
Project |
State |
Capacity (MW) |
|
Dihang Upper |
AP |
11,000 |
|
Dihang Lower |
AP |
1,700 |
|
Dihang Middle |
AP |
700 |
|
Subansiri Upper |
AP |
2,500 |
|
Subansiri Middle |
AP |
2,000 |
|
Subansiri Lower |
AP |
2,000 |
|
Parbati-III |
HP |
520 |
|
Chamera-III |
HP |
231 |
|
Bursar |
J&K |
1,020 |
|
Pakal Dul |
J&K |
1,000 |
|
Uri-II |
J&K |
280 |
|
Sewa-II |
J&K |
120 |
|
Total |
|
23,071 |