Illustrative image – not actual.The NHPC has chalked out a Rs 30,000-crore capex plan during the 12th Five Year Plan (2012-17) to set up 14,000 MW of hydro power projects. While the company intends to borrow 70 per cent of the capital required, the remaining will be raised via equity.
The company has earmarked a capex of Rs 4,600 crore for the current fiscal, of which Rs 2,000 crore has already been invested.
A total of 16 projects with a total capacity of 14,000 MW in Uttarakhand, Arunachal Pradesh and Jammu & Kashmir are in the pipeline for the next plan period.
According to sources, the 3,000 MW Debang project in Arunachal Pradesh is likely to come in 2020. Besides, NHPC will commission three units of Subansiri Lower aggregating to 750 MW in the current fiscal. However, the remaining five units accounting for 1,250 MW are likely to be commissioned in 2013.