Illustrative image – not actual.National Hydro-Electric Power Corporation is considering abandoning the 710 MW Koel Karo hydel power project, that was proposed to come up at Ranchi in Jharkhand. NHPC has cited the lack of interest of the Jharkhand state government as the main reason for considering this move.
It
is understood that the 200-odd workers that have been posted on the project
site at Torpa in Ranchi are gradually being shifted to other NHPC project
sites. The project, first conceived nearly 25 years ago, has failed to
materialize owing to stiff opposition from locals. As per the project plans,
the power plant was to come up over 22,000 hectares of land and would have
resulted in the relocation of about 38,000 people from 131 villages.
Since
its inception on 15 November 2000, the Jharkhand government has not taken
proactive steps in expediting the project, through negotiations with NHPC.
Further, it is also learnt that the Jharkhand State Electricity Board (JSEB)
has claimed that it would be power surplus in the first quarter of 2002,
leaving little incentive for the state government to pursue the Koel Karo
Project. In fact, from 2002 onwards, JSEB would even begin selling power to
Power Trading Corporation and Damodar Valley Corporation.