NHPC initiates wet commissioning of Unit-4 at 2,000 MW Subansiri Lower HEPIllustrative image – not actual.

NHPC has successfully begun the wet commissioning of Unit-4 (250 MW) at the 2000 MW Subansiri Lower hydroelectric project (HEP), marking a major milestone in India’s largest hydroelectric project.

The mechanical run of the fourth unit was completed, officially starting the commissioning process, and synchronization with the national grid has now commenced. The project consists of eight units of 250 MW each, and phased commissioning of the remaining four units will follow to achieve the full 2000 MW capacity. The milestone highlights NHPC’s engineering excellence and its pivotal role in advancing India’s clean, green, and self-reliant energy objectives. Rajendra Prasad, Executive Director and Head of Project, led the Subansiri team, ensuring the timely commissioning of Unit-4.

The successful initiation of Unit-4 not only strengthens India’s renewable energy portfolio but also underscores the strategic importance of the Subansiri Lower HEP in supporting the nation’s hydroelectric capacity expansion, enhancing grid stability, and contributing to sustainable energy generation.

← All latest storiesBack to top →