NHPC finalises location for Hydel power plant Illustrative image – not actual.

NHPC has finalized the location for setting up Bursar hydropower project at Pakal in the state of Jammu & Kashmir.


NHPC has finalized, Pakal as the suitable location for implementation of Bursar 1,020-MW HEP after considering two dam sites, Hanzal and Pakal in Jammu & Kashmir. NHPC is now planning to carry out the detailed survey and investigation and preparation of a detailed project report for this project.


Earlier, the project was kept on hold due to pending clearances and the security situation at the project site. However, the project recently started to gain momentum after the Ministry of Environment and Forests accorded clearances for pre-construction activities and approved terms of references for the project in October 2012.


The Bursar hydropower project will have four units of 255 MW each. The total estimated cost of this project is Rs 4,378 crore.

 

Related Link:
Project profile

 

← All latest storiesBack to top →