Illustrative image – not actual.NHPC is facing cost over-run hurdles for its five power projects due to local opposition and contractual issues as well as delays in receiving environment and other regulatory clearances.
The expenditure on the projects - Teesta Low Dam-IV in West Bengal, Subansiri Lower in Arunachal Pradesh, Parbati-II in Himachal Pradesh, Nimmo Bazgo and Uri-II in Jammu & Kashmir - in various stages of construction, has exceeded the amount that was initially sanctioned.
These projects have a combined capacity of 3,345 MW.
The original cost of the state-run company's Parbati-II project, with 800 MW capacity in Himachal Pradesh, which is facing contractual issues, was Rs 3,919.59 crore and the revised expenditure now stands at Rs 5,365.70 crore.