NHDP-Phase II beset by land acquisition problemsIllustrative image – not actual.

According to reports, National Highways Authority of India has so far acquired less than 15 per cent of the total land required for Phase II of the National Highways Development Programme. While NHAI has awarded a large number of contracts, physical work is getting delayed due to tardy progress on the land acquisition front.

While a total of 374 contracts have been awarded between January 2004 and January 2006, only 232 km of highways were actually four-laned till January 2006.

The total land required for NHDP-II is an estimated 15,891 ha, out of which only 2,369 ha  (less than 15 per cent) was acquired till January 2006.

Click here for state-wise details.