NHDP-Phase I completion by December 2005Illustrative image – not actual.

The Golden Quadrilateral project representing Phase I of the National Highway Development Project (NHDP), which was scheduled to be completed by June 2003, would be substantially completed by December 2005.

Minister of State for Shipping, Road Transport & Highways, Mr KH Muniyappa, listed a number of problems being encountered in the implementation of the project. These include delay in land acquisition and shifting of utilities, delay in the forest/environmental clearances, delay in clearances of road over bridges from the railway ministry, poor performance of some contractors, and also due to the law and order problems in some states.

According to a ministry release, as on January 31, 2005, out of the total length of 5,846 km of the project, work for only 4,480 km was completed. Till January 31, 2005, out of the project's total cost of Rs.25,000 crore, a sum of Rs.20,115 crore was spent.