Illustrative image – not actual.National Highways Authority of India is likely to terminate a contract for a project that connects Tamil Nadu's Tuticorin port to a national highway.
The 47 km long Tuticorin port road project, which was awarded to a joint venture between Ranchi-based Mecon and GEA Energy Systems in February 2004, was expected to complete in August 2006. So far only 22 per cent of the project work has been completed.
It is learnt that the project had been delayed as NHAI had failed to acquire and hand over land for the road. While NHAI says it has been unable to deliver a 2 km stretch, Mecon claims that over 50 per cent of the land had not been handed over. Mecon also maintains that NHAI had not proposed 'termination', and had rather agreed to declare the project closed on an 'as on' basis.
This makes it the third such contract to be cancelled, after a similar debacle involving road projects connecting Kochi and Haldia ports.
Also See:
NHAI terminates port connectivity projects (01-May-07)
Related Links:
Project
profile