National Highways Authority of India (NHAI) has decided to reward and penalise construction contractors to keep a check on timely completion of the National Highway Development Programme projects, comprising the Golden Quadrilateral (GQ) and the north-south and east-west corridors.

 

NHAI plans to give the contractors a bonus of one per cent of the project cost for early execution of works by one month up to a maximum of six per cent for eight months. However, for a delay of one month, NHAI plans to impose a penalty of 1.5 per cent on the project cost. 

 

A review of NHDP revealed that till 16 April 2001, a stretch of 769 kms of the GQ was completed and civil work contracts for 2,269 kms had been awarded. Contracts for the remaining 2,623 kms of the GQ would be awarded by July 2001. While the GQ was scheduled for completion by 2003, the north-south and east-west corridors are scheduled for completion by 2007.