Illustrative image – not actual.National Highways Authority of India (NHAI), will soon construct Kazhakuttom-Inchivila, a part of the 212 km NH-47 bypass.
The project will be executed under the BOT concept. Initially, NHAI will start 4-laning of the 27 km from Kazhakuttom to Kottukal where land has already been acquired, and later it will start work on the remaining 15 km. The entire stretch is expected to be completed in 36 months. The acquisition of the remaining 70.65 ha, on the 17 km Kottukal-Karode stretch, is expected to be completed within 4 months. Due to delay in land acquisition, work on the bypass had come to a standstill.
As a part of this, nearly 25.26 ha will have to be additionally acquired on the 22 km Kazhakuttom-Kottukal stretch for bridges, culverts, and viaducts to facilitate widening of the 2-lane road to 4-lane. Construction of 4 major bridges, including a new bridge at Akkulam, 60 culverts, 1 rail overbridge at Chakka, and 11 underpasses are part of the project.