Illustrative image – not actual.National Highway Authority of India (NHAI) is likely to complete the Vallarpadam road upgradiation project by December 2014.
The undertaking involves the four-lane National Highway connectivity to International Container Trans-shipment Terminal (ICTT) on NH-47C of 17.2 km at Vallarpadam in Ernakulam district of Kerala.
The project, which was scheduled for completion in early 2010, was delayed on account of various clearances. The original Rs 329.47 crore venture has so far seen an expenditure of Rs 932 crore. Of the total 17 km, NAHI has funded 15 km of the project and has also completed that stretch. While the remaining two km of it is yet to be constructed.
Once completed, the road link will connect Vallarpadam with two national highways.