Illustrative image – not actual.The 19.21 km road project stretch is from section of NH-73 from 157.19 km to 176.40 km (Package-III) in Haryana. The scope of Rs 248.97 crore road development includes four major bridges, three major junctions, 25 minor junctions, one flyover, one vehicular underpass, one pedestrian underpass, two overhead bridges for crossing, 10 bus bays and nine km long service road on both sides.
In 2016, NHAI had issued letter of award (LoA) to Gawar Construction for project execution on engineering, procurement and construction (EPC) basis. Till date, work on 14 km of the 19.21 km has been completed.
In a recent interaction, the promoter shared with Projects Today that since around 75 percent work on the project has been completed, they are hopeful of completing the project by March 2019, two months prior to its originally scheduled completion date of 31 May 2019.