Illustrative image – not actual.On 17 January 2007, National Highways Authority of India terminated contracts of Essar -UEM consortium for constructing two stretches of the Golden Quadrilateral between Mumbai and Chennai due to non-performance. The consortium includes Essar Constructions and UEM of Malaysia.
The two Essar contracts that have been terminated are - 77 km Chitradurga-Harihar and 56 km Harihar-Haveri link in Karnataka. The two projects were expected to be completed by August 2004 but achieved respective completion proportions of 71 per cent and 69 per cent, up to 31 December 2006.
The projects are now scheduled for completion by 2008-09 after re-award.
The Chitradurga-Harihar project was to be executed at a cost of Rs.265 crore while Rs.263 crore has already been spent. Similarly, the Harihar-Haveri link that required a total investment Rs.201 crore saw exhaustion of funds by 31 December 2006.
Meanwhile, Essar is progressing on schedule with another project -- Chitradurga-Sira section of 66.7 km -- that is part of the Mumbai-Chennai arm of the Golden Quadrilateral.