NHAI terminates port connectivity projectsIllustrative image – not actual.

The Ministry of Shipping, road transport & Highways has terminated port connectivity contracts - Kolaghat-Haldia port connectivity project, New Mangalore Port connectivity project, Tuticorin and Cochin Port connectivity projects.

The contract for the 53 km Kolaghat-Haldia port stretch on NH-41 was terminated due to the poor performance of the contractors. The project was awarded to China National Water Resources and Hydro Power Engineering Corporation-Harishchandra India on 24 July 2002. The work was to be completed by March 2005. However, despite three extensions, in January 2006, August 2006 and February 2007, only 41 per cent of the project work was complete, even though its deadline had been shifted to June 2007.

For the New Mangalore port connectivity, Ircon International has spent only Rs.9 crore. The length of the projects is 37 km on NH-17, NH-48 and NH-13. The project is estimated to cost Rs.196 crore and is scheduled for completion by December 2007.

Ranchi-based Meacon has failed in both the projects it has undertaken - the Tuticorin and the Cochin Port connectivity projects.

← All latest storiesBack to top →