Illustrative image – not actual.The NHAI has terminated a concession agreement with IRB Infrastructure Developers.
The NHAI has called off the pact due to their inability to provide necessary land for implementation of the project. In this regard, SPV IRB Goa Tollway will claim compensation as per termination payment provisions of the concession agreement.
In January 2010, the NHAI had issued a LOA to IRB Infrastructure for four laning of Goa/ Karnataka Border to Panaji - Goa stretch of NH-4A from Km 84.000 to Km 153.070 in Goa on BOT Toll Basis on DBFO pattern. The company had subsequently formed a SPV i.e. IRB Goa Tollway for implementation of this project. IRB Goa had signed the concession agreement with the NHAI in February 2010 and subsequently the project had also achieved financial closure in March 2010. Construction period of the project was 30 months.