The National Highways Authority of India’s (NHAI) wholly-owned special purpose vehicle (SPV) plans to raise Rs 46,000 crore in debt over the next two-three years to part-finance Rs 93,000 crore Delhi-Mumbai Expressway project.
The entire debt will be raised at the SPV level and the borrowing will be off NHAI’s balance sheet. In FY21, the SPV need to borrow a little less than Rs 10,000 crore, but it has already received offers for Rs 29,000 crore from banks and financial institutions. The authority will see the best rate and then decide accordingly.
DME Development, the SPV is set up for the 1,261 km expressway that is being built on the engineering procurement and construction (EPC) model in which the authority bears all the expenses.
Earlier in 2020, NHAI conceived the idea of floating project-specific SPVs, especially for the large ones. The aim was to diversify its resource base and develop self-liquidating approach to raise finances for such projects.
As per the plan, the SPV will raise debt on its balance sheet, while NHAI will retain operational control during construction, operation and maintenance of the project.
The toll on the projects housed in the SPV will be collected by NHAI, and SPV will receive the annuity payments without any construction and tolling risks. NHAI plans to form similar SPVs for other mega value highway projects.
NHAI had a debt of Rs 2.28 lakh crore as of February 2020. Such EBRs typically mask the Centre’s fiscal deficit by shifting the borrowing on to the balance sheet of the entities concerned. It is authorised to raise Rs 65,000 crore in debt for FY21.
DME Development was formed by clubbing the upcoming greenfield project with the existing highway road on Delhi-Mumbai corridor. The construction of the project, touted to be the longest one so far, is expected to be completed in three years.
The toll collections from the existing Delhi-Mumbai stretch in addition from the upcoming expressway will be used to repay the debt. NHAI will chip in if there is any deficit in the repayment obligation vis-à-vis toll collections.
Around 90 percent of the required land for the project has already been acquired and 85 percent of the project length has been awarded. The construction work has already started on 591 km stretch. NHAI has borne all expenses until now, using its own resources. The new expressway will serve as an alternative to the existing route along the 1,440 km long NH-48.
The reduction in distance is also estimated to save around 320 million ltr of fuel per annum. Moreover, reduction in distance between Delhi and Mumbai is expected to reduce by eight to nine percent logistics costs on the corridor and estimated to result in a saving of Rs one lakh crore to the economy over lifetime of the stretch.