NHAI signs agreements for three highway projectsIllustrative image – not actual.

National Highways Authority of India, on 19 October 2006, signed three concession agreements  for four-laning a total of nearly 150 km of national highways on BOT (Build-Operate-Transfer)-Annuity basis in Uttar Pradesh and Madhya Pradesh. All the three stretches are part of NHDP-Phase II (North South Corridor) and will involve a total investment of Rs.900 crore.

 As per the agreement, the concessionaires  will be responsible for the design, construction, finance, operation and maintenance of the highway stretches.

The salient features of the three projects are:

 

Jhansi-Lalitpur Section (km 0.0 to km 49.70) [NH-25/26]
Uttar Pradesh

Total length

49.70 km

Total Project Cost

Rs.355.06 crore

Construction period

30 months

Concessionaire

Gayatri-Jhansi Roadways Ltd.

(SPV formed by Gayatri Projects Ltd – IDFC Consortium)

Bypasses

5

Service Road

2.65 km

Bridges

9

Vehicular Underpasses

10

ROB (Railway Over Bridge)

1

Bus Bays

3

 

 

 

Jhansi-Lalitpur Section (km 49.700 to km 99.005) [NH-26]
Uttar Pradesh

Total length

49.305 km

Total Project Cost

Rs.276.09 crore

Construction period

30 months

Concessionaire

Gayatri-Lalitpur Roadways Ltd

(SPV formed by Gayatri Projects Ltd – IDFC Consortium)

Bypasses

4

Service Road

10.15 kms

Bridges

20

Vehicular Underpasses

7

Bus Bays

4

 

 

Lakhnadon (Km 547.400) to start of Seoni Bypass (Km 596.750) [NH-7]
Madhya Pradesh

Total length

49.350 km

Total Project Cost

Rs.263.17 crore

Construction period

30 months

Concessionaire

Malaxmi Highway Pvt Ltd (SPV formed by Nava Bharat Ventures Ltd, Hyderabad)

Bypasses

2

Service Road

675 m on both sides

Bridges

11

Vehicular Underpasses

3