Illustrative image – not actual.The NHAI has reportedly approved that all projects where the value change after restructuring was below 20 per cent of the total project cost (TPC) will be cleared by the board. The ones with over 20 per cent variation will be referred to the Union Government for approval.
This is expected to fast-track clearance of the restructured highway projects. Nearly 35 projects tendered during 2008 were restructured till June 2009 after these received no bidders. The TPC of most of these projects was increased after re-assessment of engineering was done.
The NHAI board has agreed that projects cleared by the board should not need PPP Appraisal Committee clearance. However, it will refer the case to the ministry for its nod.