Illustrative image – not actual.The National Highways Authority of India has awarded provisional completion certificate to Dilip Buildcon for early completion of a road project.
The certificate was issued and entitled for toll collection due to early completion i.e 261 days prior of the actual completion date.
The scope of work envisages four-laning of Guna-Blaora section of NH-3 from 332.100 km to 426.100 km in the state of Madhya Pradesh under NHDP Phase-IV to be executed on BOT (toll) mode on DBFOT basis.
The cost of the project is Rs 901.32 crore. The appointed date of the project was 7 September 2016 and the completion period was 910 days with a scheduled completion date of 6 March 2019.
The provisional completion date of the project is 18 June 2018.
