The National Highways Authority of India (NHAI) has issued a Letter of Award (LOA) to Gawar Construction for development of four laning of Panchkula-Yamunanagar section from km 157.192 to km 176.400 (19 km) in the state of Haryana, under NHDP Phase-III. The estimated cost of the project is Rs 249 crore.
Development of Panchkula-Yamunanagar section will improve connectivity to various villages and towns.
The project has been divided into three packages. Package-I and Package-II have already been awarded on EPC mode. The balance length of 19 km, which starts from km 160.356 near Barwala town and ends at km 179.249 at Panchkula, has now been awarded on EPC mode. The project will be completed in 24 months from the date of commencement of the project.
It will have four major bridges, three major junctions, 25 minor junctions, one flyover, one vehicular underpass, one pedestrian underpass, two overhead bridges for crossing, 10 bus bays and a nine km long service road on both sides.