Illustrative image – not actual.NHAI has declared 18 April, 2013 as appointed date for Sadbhav Engineering for execution of road project in the state of Rajasthan.
The project involves implementation of four laning of Gomati ka Chauraha-Udaipur section of NH-8 (from Km 177/000 to Km 260/100) under NHDP Phase IV, on Design, Build, Finance, Operate and Transfer (toll) basis.
The concession period is for 27 years including construction period of 910 days and it will commence from 18 April, 2013.
The project is to be executed through the company's special purpose vehicle -- Shreenathji-Udaipur Tollway.
Sadbhav Engineering had emerged as the lowest bidder for execution of the project, last year.