Illustrative image – not actual.National Highways Authority of India (NHAI) has declared 9 October as the appointed date for a road widening project in Rajasthan.
The project involves four laning of Rajsamand (NH-8)-Gangapur-Bhilwara (NH-79) in section NH-758 (from 0.00 km to 87.250 km) in the state, on DBFOT, toll basis.
The project is being executed by Bhilwara-Rajsamand Tollway, an SPV of Sadbhav Engineering.
In November 2012, Sadbhav Engineering had been selected as the successful bidder for execution of the project. The company had secured a contract worth Rs 778 crore for widening of the 87 km stretch of NH-79.
The concession period of 30 years, including construction period of 910 days will start from the appointed date.