Illustrative image – not actual.The National Highways Authority of India (NHAI) has declared the appointed date of Sangli-Solapur road project for DBL Borgaon Watambare Highways, a wholly-owned subsidiary of DBL Buildcon. The declared appointed date is 22 April 2019.
The scope of work involves four-laning of Sangli-Solapur (Package-II-Borgaon to Watambare) section of NH-166 from the existing ch 219.956 km to ch 272.394 km (design ch 224.000 km to 276.000 km) of length 52 km in the state of Maharashtra on hybrid annuity mode (HAM).
The project will entail an investment of Rs 1,029.40 crore with a construction period of 24 months. The operation period of the project is 15 years from commercial operation date (COD).