NHAI commence work on eastern peripheral expresswayIllustrative image – not actual.

The construction work on the Rs 5,763-crore eastern peripheral expressway has begun as the government has set a deadline of 400 days to complete the project.

NHAI has commenced work on some of the six packages of the 135 km expressway. The land acquisition for the project under National Highway Act, 1956 is almost complete as 98.1 land for the project has been acquired.

The project work has been divided into six packages - 21 km stretch in Sonepat-Baghpat, 24.5 km stretch in Baghpat-Ghaziabad, 24.5 km stretch in Ghaziabad-GB Nagar, 22 km stretch in GN Nagar, 21 km stretch in GN Nagar-Faridabad and 22 km stretch in Faridabad-Palwal.

The project area spans Delhi, Haryana and Uttar Pradesh.