Illustrative image – not actual.The National Highways Authority of India (NHAI) has issued a notice of intention to terminate the work given to Essel Infraprojects. The work involves widening of NH-44 into 12 lanes, including eight main lanes and four service lanes.
The project of widening the highway from Mukarba Chowk in Delhi to Panipat in Haryana has not only missed its April 2019 deadline but only 44 percent of the work has been completed so far.
The delay caused a lot of inconvenience to commuters, forcing them to face frequent traffic jams. The project worth Rs 2,128.72 crore was allotted to Essel Infraprojects in 2015 in the public-private partnership (PPP) mode. The 70 km stretch was scheduled to have 29 minor bridges, 10 flyovers, five vehicular underpasses, five passenger underpasses, 11 foot-over-bridges (FOBs) and 15 major road junctions.
The company stopped work on all sites -- flyovers, underpasses, underbridges, service lanes and other structures -- around one-and-a-half years ago. The company had allotted the work to sub-contractors who left the work midway after they didn’t get the payment on time.
The work wasn’t resumed despite several notices served by NHAI. Now NHAI has served the notice of intention to terminate the project and the matter now rests with the bank which provided loan to the company to complete the project. The bank now has to decide whether NHAI or some other private company would complete the project.