Illustrative image – not actual.The National Highways Authority of India (NHAI) has started partial trials on the 43.8 km Gurgaon-Pataudi-Rewari highway.
This would allow vehicles to use completed sections while construction continues on remaining flyovers and service roads. The corridor is being developed as a four-lane highway with two-lane service roads on both sides. The project includes 19 flyovers, a railway overbridge at Pahari. Several major structures are expected to be completed in the coming months, enabling additional sections to open for traffic.
Work on the Dwarka Expressway flyover has been delayed due to the relocation of a 400kV transmission line owned by Delhi Transco. The line is expected to be shifted by November, after which the remaining structural and approach works will proceed.
.
.