NHAI awards three BOT contracts under NHDP-IIIAIllustrative image – not actual.

National Highways Authority of India, on 6 December 2006, awarded three highway development contracts under NHDP-Phase III-A. The stretches aggregating 206 km are spread over Chhattisgarh, Maharashtra and Punjab.

The projects will be developed on BOT basis with a concession period of 20 years including construction time of thirty months.

The details of the contracts are as follows:

State

NH No.

Section

Length

Grant
(Rs. crore)

Concessionaire

Chhattisgarh

6

End of Durg bypass, Chhatisgarh/Maharashtra border

82.6
 (km 322.4 to km 405)

 (-) 0. 29

Ashoka-IDFC Consortium, Nashik

Maharashtra

6

Chhatisgarh/Maharashtra border-Wainganga Bridge

80
(km 405 to km 485)

10

Ashoka-IDFC Consortium, Nashik.

Punjab

21

Kurali-Kiratpur

42.9
(km 28.6 to km 73.2)

43.92

BSCPL-C&C Consortium Hyderabad.

So far, under NHDP Phase III A, a total of 21 contracts spanning around 1,326 km have been awarded.

Backgrounder: In March 2005, the Centre approved upgradation and four-laning of 4,000 km of National Highways on BOT basis under NHDP Phase-IIIA at an estimated cost of Rs.22,000 crore (2004 prices). The Government also approved preparation of DPRs for another 6,000 km under another sub-phase NHDP-Phase IIIB, taking the total to 10, 000 km under this Phase.

The objective of NHDP-Phase III is to 4-lane high density traffic corridors not covered by NHDP Phase-I (mainly the Golden Quadrilateral) and NHDP Phase-II (North-South and East-West corridors), connect state capitals with Phase I and Phase II and link centers of tourism and places of economic importance.

Also See:

ADB approves Rs.828 crore loan to rural roads programme (31-Aug-06)

← All latest storiesBack to top →