Illustrative image – not actual.National Highways Authority of India, on 13 April 2006, awarded five cash contracts for highway development in Madhya Pradesh. The contracts, valued at nearly Rs.900 crore, involve four-laning of 220 km of highways along NH-26 in Madhya Pradesh.
While four contracts valued at Rs.702.38 crore were awarded to South Korean firm, Sang Yong Engineering & Construction Co, one contract was given to B Seenaiah & Co (Project) Ltd.
The projects are being implemented with financial assistance from Asian Development Bank, and are part of NHDP-II (North-South, East-West Corridor).
The broad details of the five contracts are:
| Stretch | Length (km) |
Milestone |
Cost (Rs.crore) |
Contractor | Construction
period (months) |
|
| From | To | |||||
| Sagar Bypass | 26 | 187 | 211 | 116.00 | SYECCL | 30 |
| Jhansi-Lakhnadon | 44 | 211 | 255 | 163.87 | SYECCL | 30 |
| Jhansi-Lakhnadon | 54 | 297 | 351 | 219.01 | SYECCL | 30 |
| Jhansi-Lakhnadon | 54.7 | 351 | 405.7 | 203.50 | SYECCL | 30 |
| Jhansi-Lakhnadon | 42 | 255 | 297 | 189.63 | BSCPL | 30 |
| Total | 220.7 | 892.01 | ||||