NHAI approves investment proposals for three BOT projectsIllustrative image – not actual.

On 4 July 2007, National Highways Authority of India (NHAI) accorded investment approval for design, engineering, finance, construction, operation and maintenance of three projects in  Bihar, Madhya Pradesh & Haryana on BOT basis and are a part of NHDP Phase-IIIA. The projects are:

NH No Section State Approx. Length (km) Project Cost (Rs.in crore)
77 Patna-Muzaffarpur Section of NH-77 with a 17.071 km bypass to Muzaffarpur connecting NH-28 Bihar 63.371 458
3 Khalghat-MP/Maharashtra Border Section Madhya Pradesh 82.800 549
10 Rohtak-Hissar Section Haryana 89.36 543

The concession period will be 18 years (including construction). PPPAC has already accorded its approval for these projects in January 2007.