Illustrative image – not actual.Neyveli Lignite Corporation has proposed to take up the following projects for which an advanced action plan has been prepared, and which has already been approved by the Central government.
1.
Tuticorin Power Project: The 1,000 MW coal-based power project is being
developed as a joint venture with the Tamil Nadu Electricity Board. The MoU for
this Rs.4,000 crore project has already been signed with TNEB.
2.
Orissa Power Project: This 2,000 MW coal-based project costing Rs.8,000
crore will be implemented singly by NLC.
Some other projects that are under formulation are:
1.
Mine
III with capacity 8 million tpa along with a coal-based power plant of 1,000 MW
(2 x 500 MW) with capital outlay of Rs.7,418 crore
2.
Power
plant of 492 MW based on refinery residue as joint venture with Chennai
Petroleum Corporation, costing Rs.2,837 crore.
3.
Power
plant of capacity 125 MW costing Rs.455.26 crore, which would use surplus
lignite that would be available from Mine III expansion project.
Four projects are currently under various stages of sanction by the Central government. These are:
1.
Mine
II Expansion (4.5 million tpa of lignite)
2.
Expansion
of TPS II (500 MW)
3.
Rajasthan
Lignite Mine expansion (2.1 million tpa)
4.
Rajasthan
Power project (250 MW)
Meanwhile, three major projects totally costing Rs.4,000 crore were commissioned during 2002-03. These are expansion of Mine I, setting up of Mine 1-A and expansion of thermal power station (TPS-1).
