Friday, July 31, 2009Office SpaceProjects Today News
Illustrative image – not actual.
McNally Bharat Engineering Company received an order valued at Rs 414
crore from Ideal Energy Projects for design, engineering, manufacturing,
supply, erection, testing and commissioning of Balance of Plant on EPC basis
including civil works for 1X270 MW coal based power project near Bela at
Nagpur, Maharashtra.
Confidence Go Gas, a wholly-owned subsidiary of Confidence Petroleum
India, has commissioned Auto LPG Dispensing Stations (ALDS) at Chopda-Jalgaon
(Maharashtra), Cuddapah (Andhra Pradesh) & Prodattur (Andhra Pradesh).
ISMT has decided to enter the infrastructure business by setting up a 150
MW power project in Tamil Nadu to be implemented under a SPV.
PGCIL board has approved the Rs 1736.36 crore investment for the 765 kV
System for Central Part of Northern Grid - Part -II with commissioning
schedule of 30 months from the date of investment approval matching with the
commissioning of transmission lines of Part-I. (The 765 kV System for Central
Part of Northern Grid - Part-I has already been approved by the Board in
February 2009).