  • Adani Power (APL) on 22 December 2010 synchronised Unit V of 660 MW capacity under Phase III at Mundra in Kachchh district of Gujarat. With this new unit, APL will have 1,980 MW generation capacity at Mundra.
     
  • Aster Silicates, a manufacturer of silicates on 23 December 2010 began the Phase I commercial production with 150 tpd capacity at its Bharuch plant in Gujarat. The entire project will be completed by March 2011.
     
  • Work on the Phase III of the Delhi Metro Project is likely to begin in April 2011.
     
  • Mundra Port and Special Economic Zone on 23 December 2010 has commenced operations on the 60 million tonne fully mechanised coal handling terminal at Mundra in Gujarat.
     
  • Pipavav Shipyard has signed an MoU with SAAB Dynamics AB (SAAB), a part of Sweden based Wallenberg Group. This is a major defence co-production initiative taken by the Wallenberg Group in India and this MoU will enable Pipavav Shipyard to enter into army and air force segments.