The Board of Directors of PGCIL on 15 April 2010 has approved the
investment for "transmission system for development of pooling station in
northern part of West Bengal and transfer of power from Bhutan to NR/WR" at
an estimated cost of Rs 4,404.57 crore, with commissioning schedule of 57
months tentatively from the date of investment approval.
Petron Engineering Construction bagged an order worth Rs 180 crore from
Indian Oil Corporation for design, detailed engineering, procurement,
construction including total project management and handing over of complete
AVU Fired Heaters on a Single Point Responsibility Basis for
Paradip Refinery Project.