News in Brief: 01 November 2010Illustrative image – not actual.
  • MSP Steel & Power has started operation of its 1,15,500 tpa of sponge iron plant and 18 MW power plant. With this commissioning, the total capacity of sponge iron plant has increased from 1,92,000 to 3,07,500 tpa & power plant from 18 to 42 MW. The generated will be used both for captive purpose as well as for merchant sale.
     
  • Godawari Power and Ispat’s biomass based power plant with a capacity of 20 MW has been successfully completed and the plant has started commercial generation of power from 1 November 2010 at Siltara Industrial Complex, Raipur in Chhattisgarh.