Illustrative image – not actual.Airports Authority of India (AAI) is expected to complete work on the new integrated terminal building of Madurai airport in Tamil Nadu, by March 2010.
So far, AAI has completed work on construction of the main terminal building and an additional electricity sub-station. Electrical equipment such as transformers and diesel generator sets had been put in place. Currently, roofing and car parking works is on. AAI has placed orders for baggage carousels and other systems.
The new integrated terminal building to be spread over 17,560 sq mtrs is likely to be a centrally air-conditioned building with 20 immigration counters, 27 customs counters and two aerobridges. It is expected to handle 250 arriving and as many departing passengers as against the total capacity of just 150 passengers in the existing building.
Besides, AAI had planned to extend the runway from the existing 7,500 mtrs by another 3,000 mtrs. Currently, land acquisition is underway for around 600 acres by the Tamil Nadu Government.