Illustrative image – not actual.The Union Railway Minister, Mr Nitish
Kumar, will be laying the foundation stone for a new railway station at Mumbai,
on 20 March 2003.
The new railway station, Nahur, will be
coming up between the Bhandup and Mulund stations of the Central Railway line in
Mumbai. Expecting to cost Rs.2 crore, Nahur would be commissioned by March
2004. The Napur Railway Station was sanctioned in the Railway Budget for
2003-04.
The present distance between the
Bhandup and Mulund stations is 4.41 km, which is much above the average
inter-station distance of 1.71 km, on the Central Railway line. Nahur would be
equidistant from Bhandup and Mulund.
Nahur would be the first railway
station to be constructed in Mumbai after a gap of 35 years – the last station
constructed was Kanjur Marg also on the Central Railway line between Vikhroli
and Bhandup, in 1968.