Illustrative image – not actual.The
Central government along with the Tamil Nadu state government and financial
institutions have reportedly agreed on a new payment security mechanism for the
Ennore Power and LNG projects. This new mechanism would provide the project
promoters with some kind of an escrow cover, the absence of which has delayed
the project inordinately.
It
has been agreed that a separate fund will be created out of the devolvement of
tax revenues to Tamil Nadu from the Centre. Collections from this fund are
estimated at Rs.80 crore per month, of which Rs.30 crore or so, would be set
aside for creating the payment security cover.
This
proposal, which has been cleared by the state government, has yet to be
approved by the Centre.
The
Ennore project is being implemented by Dakshin Bharat Energy Consortium (DBEC),
which comprises five entities — Grasim Industries, CMS Energy and Unocal
Corporation (both of US), Siemens of Germany and Woodside Petroleum of
Australia. The capital outlay of the
project is around $1426 million (approx. Rs.6,400 crore).
The
scope of the project includes:
- Construction of an
LNG Terminal at Ennore, in Chennai, with a capacity of 2.5 million tonnes
per annum
- Development of a 1850
MW Power plant gas based power plant.
The
first phase of the power plant was scheduled for completion by August 2003, but
this is unlikely to materialise.